Every plant, reported every month.
Each owner receives a report every month. The one on this page is built from Ballito Lifestyle Centre, a plant Sunbird Solar built.
Request a site assessmentThe report, section by section
Each note says how the number is produced and the question a board should ask about it.
Monthly performance report
Ballito Lifestyle Centre, 2,036 kWp, built by Sunbird Solar
2,511MWhMeasured
Generated in the last measured year
- Estimated annual client saving
- R6.0mEstimated
2,350 MWh generated against a forecast of 2,003 MWh, Nov 2025 to Sep 2026. Measured.
+17% vs forecast
| Month | Measured | Forecast |
|---|---|---|
| Nov 2025 | 276,828 | 222,359 |
| Dec 2025 | 255,250 | 226,058 |
| Jan 2026 | 298,622 | 238,060 |
| Feb 2026 | 260,520 | 207,964 |
| Mar 2026 | 238,215 | 204,512 |
| Apr 2026 | 180,506 | 168,804 |
| May 2026 | 170,634 | 145,135 |
| Jun 2026 | 136,146 | 120,176 |
| Jul 2026 | 157,989 | 133,081 |
| Aug 2026 | 185,497 | 156,642 |
| Sep 2026 | 190,280 | 180,493 |
- Ballito Lifestyle CentreOver two full measured years
- 1,234 kWh/kWpMeasured
- The 68 sites with verified performance dataCapacity-weighted, July 2026
- 1,112 kWh/kWp
Generation against expected
Daily generation from the revenue meter, set against what the plant’s yield model gives for the month’s conditions.
Ask: On which days did generation fall below expected, and why?
Specific yield and performance ratio
Specific yield is kWh per kWp installed, so plants of different sizes can be compared. Performance ratio, as IEC 61724-1 defines it, also allows for the sunlight the plant received.
Ask: Is the year’s yield in line with the plant’s design estimate?
Availability
Shown as the generation lost to outages, in kWh, so a percentage cannot hide a costly day.
Ask: What did each outage cost?
Faults raised, resolved and open
Every fault from its first alarm to the close-out, with the cause and the action taken.
Ask: Which faults are still open, and since when?
Savings value
The value of generation at the site’s blended tariff, as in the client’s own reports. Labelled Estimated, because the tariff is an input, not a reading.
Ask: Which tariff was used, and is it current?
Maintenance completed
Tasks planned for the month set against tasks done.
Ask: What was carried over, and why?
Next month’s planned work
The work planned for the coming month, so the next report can be checked against it.
Ask: Does the plan match the faults and findings above?
Five rules every report follows
How every report on this site is produced.
Metered, not estimated
Generation is read from revenue meters and monitoring platforms, then reconciled against the monthly production report issued to each client.
Measured and modelled are kept apart
Every site is tagged. Where a plant has run less than a full year, output is annualised and labelled as such, never presented as an actual.
Built and taken over are kept apart
Sites Sunbird Solar designed and installed are reported separately from sites taken over under O&M.
Contract terms stay private
Performance guarantees and commercial terms never appear in portfolio reporting.
Every figure is traceable
Each number resolves to a named site, a commissioning date and a monitoring platform.
The fund view
A fund with many centres sees every plant reported the same way, side by side, with plants Sunbird Solar built kept apart from plants taken over from other installers.
Portfolio summary
Five centres, July 2025 to June 2026
- Centres
- 5
- Built by Sunbird Solar
- 2,300 kWp
- Taken over
- 3,400 kWp
| Centre | kWp (rounded) | MWh, July 2025 to June 2026 | Specific yield, kWh/kWp |
|---|---|---|---|
| Built by Sunbird Solar | |||
| Centre A | 1,400 | 1,686.1 | 1,167 |
| Centre B | 900 | 1,296.8 | 1,465 |
| Total built by Sunbird Solar | 2,300 | 2,982.9 | 1,280 |
| Taken over | |||
| Centre C | 1,300 | 1,833.6 | 1,429 |
| Centre D | 1,300 | 1,497.8 | 1,159 |
| Centre E | 800 | 1,069.5 | 1,366 |
| Total taken over | 3,400 | 4,400.9 | 1,311 |
| Portfolio total | 5,700 | 7,383.8 | 1,298 |
Built by Sunbird Solar
Centre A
- kWp
- 1,400
- MWh
- 1,686.1
- kWh/kWp
- 1,167
Centre B
- kWp
- 900
- MWh
- 1,296.8
- kWh/kWp
- 1,465
Total built by Sunbird Solar
- kWp
- 2,300
- MWh
- 2,982.9
- kWh/kWp
- 1,280
Taken over
Centre C
- kWp
- 1,300
- MWh
- 1,833.6
- kWh/kWp
- 1,429
Centre D
- kWp
- 1,300
- MWh
- 1,497.8
- kWh/kWp
- 1,159
Centre E
- kWp
- 800
- MWh
- 1,069.5
- kWh/kWp
- 1,366
Total taken over
- kWp
- 3,400
- MWh
- 4,400.9
- kWh/kWp
- 1,311
Portfolio total
- kWp
- 5,700
- MWh
- 7,383.8
- kWh/kWp
- 1,298
Send us 12 months of meter data for any plant
We return a performance gap report, whoever built the plant. It is the first step of a site assessment.